Project Management Diploma: Schedule Development (Outputs)

biz int Project Management Diploma: Schedule Development (Outputs)Learn about Schedule Development (Outputs) in the Project Management Diploma qualification.

Project Schedule. The project schedule includes at least a planned start date and planned finish date for each schedule activity. If resource planning is done at an early stage, then the project schedule would remain preliminary until resource assignments have been confirmed, and scheduled start dates and finish dates are established.

This process usually happens no later than completion of the project management plan. A project target schedule may also be developed with defined target start dates and target finish dates for each schedule activity. The project schedule can be presented in summary form, sometimes referred to as the master schedule or milestone schedule, or presented in detail. Although a project schedule can be presented in tabular form, it is more often presented graphically, using one or more of the following formats:

  • Project schedule network diagrams. These diagrams, with activity date information, usually show both the project network logic and the project’s critical path schedule activities. These diagrams can be presented in the activity-on-node diagram format, as shown in Figure 6-3, or presented in a time-scaled schedule network diagram format that is sometimes called a logic bar chart, as shown for the detailed schedule in Figure 6-9. This example also shows how each work package is planned as a series of related schedule activities.
  • Bar charts/Gantt Charts. These charts, with bars representing activities, show activity start and end dates, as well as expected durations. Bar charts are relatively easy to read, and are frequently used in management presentations. For control and management communication, the broader, more comprehensive summary activity, sometimes referred to as a hammock activity, is used between milestones or across multiple interdependent work packages, and is displayed in bar chart reports. An example is the summary schedule portion of Figure 6- 8 that is presented in a WBS structured format. Typically project management bar charts depict the work in a project against a calendar, and these are called Gantt charts.
  • Milestone charts. These charts are similar to bar charts, but only identify the scheduled start or completion of major deliverables and key external interfaces. An example is the milestone schedule portion of

Typically a project schedule will show the actual start date, actual duration, and actual finish date for completed schedule activities, the actual start date, remaining duration, and current finish date for schedule activities with work in progress, and the current start date, original duration, and current finish date for schedule activities where work has not yet started.

For a simple project schedule, Figure 6-9 gives a graphic display of a Milestone Schedule, a Summary Schedule, and a Detailed Schedule. Figure 6-9 also visually shows the relationships among the three different levels of schedule presentation.

 

Schedule Model Data. Supporting data for the project schedule includes at least the schedule milestones, schedule activities, activity attributes and documentation of all identified assumptions and constraints. The amount of additional data varies by application area. Information frequently supplied as supporting detail includes, but is not limited to:

  • Resource requirements by time period, often in the form of a resource histogram
  • Alternative schedules, such as best-case or worst-case, not resource leveled, resource leveled, with or without imposed dates
  • Schedule contingency reserves.

For example, on an electronics design project, the schedule model data might include such items as human resource histograms, cash-flow projections, and order and delivery schedules.

Schedule Baseline. A schedule baseline is a specific version of the project schedule developed from the schedule network analysis of the schedule model. It is accepted and approved by the project management team as the schedule baseline with baseline start dates and baseline finish dates.

Resource Requirements (Updates). Resource levelling can have a significant effect on preliminary estimates of the types and quantities of resources required. If the resource-levelling analysis changes the project resource requirements, then the resource requirements are updated.

Activity Attributes (Updates). The activity attributes are updated to include any revised resource requirements and any other related approved changes generated by the Schedule Development process.

Project Calendar (Updates). A project calendar is a calendar of working days or shifts that establishes those dates on which schedule activities are worked. It also establishes nonworking days that determine dates on which schedule activities are idle, such as holidays, weekends, and non-shift hours. The calendar for each project may use different calendar units as the basis for scheduling the project.

Requested Changes. The Schedule Development process can create requested changes that are processed for review and disposition through the Integrated Change Control process.

Project Management Plan (Updates). The project management plan is updated to reflect any approved changes in how the project schedule will be managed.

  • Schedule Management Plan (Updates). If approved change requests result from the Project Time Management processes, then the schedule management plan (Chapter 6 introductory material) component of the project management plan may need to be updated to include those approved changes.

LMIT’s Diploma in Project Management is Now Endorsed by AIPM – Get Your Diploma of PM and You’ll Also Receive a Certificate from AIPM.

LMIT provides online training courses for the Cert IV Project Management BSB41507, the Certificate IV of Project Management and the Diploma of Project Management BSB51407 in Brisbane, Sydney, Melbourne, Perth, Adelaide and Canberra.

 

Published by: LMIT

Leave a Reply